Minnesota · public works / prevailing wage · Minn. Stat. §§ 177.42–177.43

After eight every day. No weekend all-hours premium.

Minn. Stat. §§ 177.42–177.43 for labor on Minnesota state-funded public works: 1.5× after 8 hours in a day and after 40 hours in a week. Saturday, Sunday, and holidays are not all-hours premiums — unlike Oregon public works (Sat/Sun/holiday all hours at 1.5×) and Missouri public works (Sunday/holiday all hours at 2×). Eight Sunday hours @ $20 basic are $160 here, $240 Oregon PW, $320 Missouri PW. A 10-hour weekday is 8 regular + 2 OT here; Missouri PW is 10 regular. Typed rate is the hourly basic rate; fringe is owed at 1× on all hours (DLI / MnDOT).

Read the statute: prevailing hours ≤8/day and ≤40/week

Official bodies fetched for this page: Minnesota Revisor § 177.41, § 177.42, § 177.43, DLI Prevailing wages for state-funded construction, DLI Know your rights, DLI state grant programs, MnDOT Labor Compliance overtime, and the DLI commercial wage notice — all HTTP 200.

Minn. Stat. § 177.42 subd. 4: "Prevailing hours of labor" means the hours of labor per day and per week worked within the area by a larger number of workers of the same class than are employed within the area for any other number of hours per day and per week. The prevailing hours of labor may not be more than eight hours per day or more than 40 hours per week.

Minn. Stat. § 177.43 subd. 1(1): … no laborer or mechanic employed directly on the project work site … is permitted or required to work more hours than the prevailing hours of labor unless paid for all hours in excess of the prevailing hours at a rate of at least 1-1/2 times the hourly basic rate of pay.

DLI Know Your Rights and MnDOT Labor Compliance: workers required to work in excess of eight hours a day or 40 hours a week shall be compensated at a rate of 1.5 times the basic hourly rate plus fringe benefits (fringe at 1× on every hour). The commercial wage notice states overtime after eight on the project must be paid even if the worker does not exceed forty in the workweek. Enter the hourly basic rate here; fringe cash is labeled, not totaled into the wage ticket. Projects under § 177.43 subd. 7 ($2,500 one-trade / $25,000 multi-trade), off-site delivery of manufactured materials (subd. 2), and highway-heavy § 177.44 classification look-ups are out of scope. Not private-sector Minnesota weekly-48 (§ 177.25) and not Minnesota meal/rest.

Weekday 10h 07:00–17:00 @ $20 basic → 8 regular + 2 OT = $220. Missouri PW: 10 regular = $200. Oregon PW without 4×10: 8+2 OT = $220.
Weekday 12h @ $20 → 8 regular + 4 OT = $280. Missouri PW: 10+2 OT = $260.
Saturday 8h @ $20 → 8 regular = $160. Oregon PW: 8 OT = $240.
Sunday 8h @ $20 → 8 regular = $160. Oregon PW: 8 OT = $240. Missouri PW: 8 DT = $320.
Five 10-hour weekdays @ $20 → 40 regular + 10 OT = $1,100.
Overnight weekday 20:00–08:00 lunch 30 @ $20 → 11.5h → 8 regular + 3.5 OT = $265. Missouri Sunday same punches: 11.5 DT = $460.

In scope

  • Minn. Stat. §§ 177.42–177.43 public works: 1.5× after 8 in a day and after 40 in a week
  • Every workday including Saturday, Sunday, and holidays — after 8 only (no all-hours weekend premium)
  • Weekly 40 leftover regular only (no pyramiding)
  • Typed rate = hourly basic rate; fringe at 1× on all hours (out of cash total)
  • Punch-in/out + unpaid lunch; Day 1 is Monday

Out of scope

  • Oregon PW Sat/Sun/holiday all-hours 1.5× — /oregon-public-works-overtime/
  • Missouri PW Sunday/holiday all-hours 2× and after-10 — /missouri-public-works-overtime/
  • Private-sector Minnesota weekly-48 (177.25); /minnesota-meal-rest/
  • Projects under 177.43 subd. 7; off-site manufactured-material delivery (subd. 2)
  • Highway-heavy 177.44 trade look-ups; zone/shift differentials; multi-class weighted OT

FAQ

When is overtime due on a Minnesota public works project?

Minn. Stat. § 177.42 subd. 4 caps prevailing hours at eight per day and forty per week. § 177.43 subd. 1(1) requires at least 1.5× the hourly basic rate for hours in excess of those prevailing hours. DLI and MnDOT: overtime after eight hours a day on the project (even under 40 in the week) and after 40 in a week, at 1.5× basic plus fringe at 1×.

Is Saturday or Sunday time-and-a-half for all hours?

No. Unlike Oregon ORS 279C.540 (Saturday/Sunday/holiday ALL hours at 1.5×) and Missouri RSMo § 290.230 (Sunday/holiday ALL hours at 2×), Minnesota §§ 177.42–177.43 have no weekend or holiday all-hours premium. Saturday and Sunday hours under eight are regular. Eight Sunday hours at $20 basic are $160 here; on /oregon-public-works-overtime/ they are $240; on /missouri-public-works-overtime/ they are $320.

Is this the same as Oregon or Missouri public works overtime?

No. /oregon-public-works-overtime/ pays Sat/Sun/holiday ALL hours at 1.5×. /missouri-public-works-overtime/ pays Sunday/holiday ALL hours at 2× and daily overtime only after 10. Minnesota is after 8 every day with no weekend all-hours premium. A 10-hour weekday @ $20 is $220 here and on Oregon PW without 4×10, but $200 on Missouri PW.

Does the typed rate include fringe benefits?

No. Enter the hourly basic rate. DLI and MnDOT: overtime cash is 1.5× the basic hourly rate, and fringe is still owed at 1× on every hour worked (including overtime hours). Fringe dollars are out of the cash-wage total on this page — same display stance as /oregon-public-works-overtime/, and opposite of /missouri-public-works-overtime/ (where DOLIR multiplies wage+fringe).